Schedule of Proposed Actions (SOPA)

This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.

Report Contents (click to jump to a section):
- White Mountain National Forest, Forestwide (excluding Projects occurring in more than one Forest)
- White Mountain National Forest , Androscoggin Ranger District
- White Mountain National Forest , Pemigewasset Ranger District
- White Mountain National Forest , Saco Ranger District


White Mountain National Forest, Forestwide (excluding Projects occurring in more than one Forest) R9 - Eastern Region
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
AMC Backcountry Facility Permit Renewal
CE
- Special use management Developing Proposal
Est. Scoping Start
06/2014
Expected: 08/2014 09/2014 Sarah LaPlante
603-536-6237
slaplante@fs.fed.us
Description: Re-issue permits for the existing backcountry facilities (shelters and tentsites) currently operated by the Appalachian Mountain Club. No additional use or increases in capacity are proposed as part of this project.
Location: UNIT - White Mountain National Forest All Units. STATE - New Hampshire. COUNTY - Coos, Grafton. LEGAL - Not Applicable Backcountry facilities operated by AMC
Administrative Radio Repeater Improvement Project
EA
- Facility management In Progress
Scoping Start
02/03/2014
Est. Comment Period Public Notice
06/2014
Expected: 12/2014 05/2015 Erica Roberts
603-536-6230
ericajroberts@fs.fed.us
Description: Install 3 new radio repeaters and relocate and enhance 1 existing repeater to increase FS radio coverage on the WMNF where good coverage is lacking and allow for Forestwide communication; includes clearing trees for helicopter use and new sites.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43438
Location: UNIT - White Mountain National Forest All Units. STATE - New Hampshire. COUNTY - Carroll, Coos, Grafton. LEGAL - Not Applicable Carr Mountain, Mount Cabot, Mount Carrigain, and Wildcat Mountain. Will remove Milan repeater.
Northern Pass Transmission Line Special Use Permit
EIS
- Special use management In Progress
NOI in Federal Register
02/11/2011
Est. DEIS NOA in Federal Register
09/2014
Expected: 09/2015 11/2015 Tiffany Benna
603-536-6241
tbenna@fs.fed.us
Description: Proposed power transmission line that would cross the WMNF in an existing corridor in Stark, Easton, Lincoln, Woodstock. US Dep't of Energy is leading the NEPA analysis. WMNF decision is whether to issue a special use permit to cross the Forest.
Web Link: http://www.northernpasseis.us/
Location: UNIT - White Mountain National Forest All Units. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable For more information, see the project website at: www.northernpasseis.us.
White Mountain National Forest , Androscoggin Ranger District R9 - Eastern Region
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Albany South Project
EA
- Wildlife, Fish, Rare plants
- Forest products
- Recreation management
- Road management
- Watershed management
In Progress
Scoping Start
07/15/2013
Est. Comment Period Public Notice
06/2014
Expected: 01/2015 04/2015 Kori Marchowsky
603-536-6108
kmarchowsky@fs.fed.us
Description: An integrated resource management project that proposes vegetation management to improve wildlife habitat and forest health conditions, as well as recreation, watershed and transportation system improvements.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=39614
Location: UNIT - Androscoggin Ranger District. STATE - Maine. COUNTY - Oxford. Town of Stoneham, Oxford County, ME
Androscoggin Ranger District Education and Wellness Trail
CE
- Recreation management In Progress
Scoping Start
03/28/2014
Expected: 05/2014 07/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Construct a loop hiking trail of ~1 mile from the Androscoggin Ranger Station, on the Fifth Hole Trail to beaver ponds, then parallel to the river back to the office. For employees and visitors, and for conservation education programs.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41627
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable Androscoggin Ranger Station, Gorham, NH
Central Maine Power Co. Special Use Permit
CE
- Special use management In Progress
Scoping Start
03/31/2014
Expected: 06/2014 07/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Issue a new special use permit to CMP for a period of 30 years. CMP proposes to install utility poles and overhead electrical lines along 1,400 feet of FR 3314 to a private inholding and residence.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42969
Location: UNIT - Androscoggin Ranger District. STATE - Maine. COUNTY - Oxford. LEGAL - Not Applicable Forest Road 3314, Mason Township, Oxford County, Maine
Central Maine Power Company Co. Special Use Permit
CE
- Special use management Cancelled N/A N/A Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Installation of overhead electrical lines along 1,400 feet of Forest Road 3314 to a private residence and inholding.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44061
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable Forest Road 3314, Mason Township, Oxford County, Maine
Glen Ellis Falls Day Use Area Site Improvement Project
EA
- Facility management
- Heritage resource management
- Recreation management
- Watershed management
On Hold N/A N/A Kori Marchowsky
603-536-6108
kmarchowsky@fs.fed.us
Description: This project proposes to repair many of the facilities--including the access road, parking, picnic sites, trails, signage and toilets--at this popular day use area.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=33106
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. Glen Ellis Falls Day Use Area
Harvard Cabin Renovations and System Upgrades
CE
- Special use management
- Facility management
Developing Proposal
Est. Scoping Start
04/2014
Expected: 06/2014 07/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Allow Harvard Mountaineer Club to replace two rotting logs in the cabin, install new windows and wood stove, and install a 30' tall tower to increase radio coverage and hold new solar panels, which will allow them to replace propane lanterns.
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. Harvard Cabin
Maple Syrup Tree Tapping Permit
EA
- Special use management Developing Proposal
Est. Scoping Start
04/2014
Expected: 10/2014 01/2015 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: 5-year special use permit to place several hundred taps in sugar maple trees on 75 acres and use of existing old skid roads for tapping effort.
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. Town of Randolph
Northern New Hampshire Bird Dog Club Special Use Permit Renewal
CE
- Special use management In Progress
Scoping Start
03/31/2014
Expected: 07/2014 07/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Renew the existing 5 year permit. The permit authorizes use of several informal walking trails, pre-approved brushing, and the authorization to hold competitive grouse and woodcock timed hunting events in September and October of each year.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42971
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable Kilkenny tract, informal trails along the Bog Dam Loop Road (FR 15), City of Berlin, Coos COunty, New Hampshire.
Parker Sugar Bush Special Use Permit Renewal
CE
- Special use management In Progress
Scoping Start
04/09/2014
Expected: 06/2014 06/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Renew the expired 5 year special use permit that authorizes maple syrup tapping on 238 acres of NFS land. The permit expired in June, 2013.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42972
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable Town of Randolph, Coos County, New Hampshire: 238 acres of NFS land in Compartment 31, stands 4, 45, and 46.
Pond of Safety Accessible Trail & Shoreline Access Hardening
CE
- Recreation management In Progress
Scoping Start
03/28/2014
Expected: 05/2014 06/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: Replace user created trail from designated parking lot to canoe launch with accessible trail along an existing road prism and harden shore using riprap to limit erosion. May include a small (3' square) landing to allow easier canoe access.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=40387
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable Pond of Safety, Randolph, NH
South Pond Road Association Special Use Permit Renewal
CE
- Special use management In Progress
Scoping Start
03/31/2014
Expected: 06/2014 06/2014 Thomas Moore
603-466-2713 x226
tmmoore@fs.fed.us
Description: The purpose of This project is to renew the existing permit for a 5 year period. The permit authorizes the road association use of Forest Roads 65, 65A and 65B to perform annual routine maintenance and snow plowing for safe public access.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=42967
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable Forest Roads 65, 65A and 65B; Town of Stark, NH
Wild River Valley Trail Repairs
CE
- Recreation management In Progress

03/07/2014
Expected: 05/2014 06/2014 Travis Pellerin
603-466-2713
tpellerin@fs.fed.us
Description: Repair the Moriah Brook Trail footbridge crossing the Wild River and relocate six small sections (totaling approximately 0.5 miles) of the Highwater Trail adjacent to the Wild River from damage that occurred during Tropical Storms Irene and Sandy.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=43261
Location: UNIT - Androscoggin Ranger District. STATE - New Hampshire. COUNTY - Coos. LEGAL - Not Applicable The proposed project includes portions of trails located in the Wild River Valley on the north side of Evans Notch. None of the proposals are in the Wild River Wilderness.
White Mountain National Forest , Pemigewasset Ranger District R9 - Eastern Region
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Bog Pond Snowmobile Trail Relocation
CE
- Recreation management
- Watershed management
Developing Proposal
Est. Scoping Start
06/2014
Expected: 07/2014 08/2014 Jennifer Burnett
603-536-6107
jburnett@fs.fed.us
Description: Reconstruct approximately 0.25 miles of the Bog Pond Snowmobile Trail so that its crossing of Harvard Brook is relocated to a more sustainable location that better protects soil and water resources.
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable Bog Pond Trail in Lincoln, NH
Bowen Brook Integrated Resource Management
EA
- Forest products
- Vegetation management (other than forest products)
- Wildlife, Fish, Rare plants
- Recreation management
- Road management
- Watershed management
Developing Proposal
Est. Scoping Start
05/2014
Expected: 08/2015 01/2016 Desiree Johnston
603-447-5448 x128
dajohnston@fs.fed.us
Description: An integrated resource project designed to move the Wild Ammonoosuc North Habitat Mgt Unit (HMU) toward desired conditions through timber, wildlife habitat, recreation, fisheries and aquatic management, road improvements and decommissioning.
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable Towns of Bath, Easton and Landaff, Grafton County, NH
Loon Mountain South Peak Learning Center
EA
- Recreation management
- Land management planning
- Special use management
In Progress
Comment Period Public Notice
04/23/2014
Est. Objection Period Legal Notice
05/2014
Expected: 08/2014 08/2014 Joseph Gill
603-466-2713 x221
jgill@fs.fed.us
Description: Allow construction of two fixed-grip chairlifts, approx. 26 acres of new or realigned teaching ski terrain and expansion of snowmaking to new area with existing water. Approx. 60% of lifts and ski terrain on NFS lands. Add'l work on private lands
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37025
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Lincoln, NH Loon Mountain Ski Area
Loon Pond Dam Repair
CE
- Watershed management
- Special use management
Developing Proposal
Est. Scoping Start
04/2014
Expected: 06/2014 08/2014 Tom Giles
603-536-6102
tjgiles@fs.fed.us
Description: The Town of Lincoln has proposed repair work for the Loon Pond Dam in order to comply with federal reqirements for the town water supply. The town has a right to use and maintain the dam for purposes specified in their deed.
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable The dam to be maintained is on Loon Pond west of Loon Mountain Ski Area in the town of Lincoln, NH.
Rumney Rocks Management Project Supplemental Analysis and Decision
EA
- Recreation management In Progress
Comment Period Public Notice
06/13/2013
Est. Objection Period Legal Notice
04/2014
Expected: 06/2014 06/2014 Tom Giles
603-536-6102
tjgiles@fs.fed.us
Description: Update Environmental Assessment to include rock removal for trail construction by either mechanical means or controlled blasting. Other trail work was covered in 2009 decision. Also adds a permanent toilet adjacent to the Main Cliff parking area.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38661
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable Rumney Rocks Climbing Area, Buffalo Road, Rumney, NH
Time Warner Cable Fiber Optic Cable Permit Issuance
CE
- Special use management In Progress
Scoping Start
04/15/2013
Expected: 04/2014 04/2014 Justin Preisendorfer
603-536-6105
jpreisendorfer@fs.fed.us
Description: Issue a 30-year permit to Time Warner Cable for existing fiber optic cable formerly under special use permit in the Town of Waterville Valley, NH
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41006
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable In the Town of Waterville Valley, NH extending from West Branch Road to the ski area and up to Schwendi Hut
Tripoli Road Campsite Relocation and Roadside Hazard Tree Removal Project
EA
- Watershed management
- Recreation management
In Progress
Scoping Start
12/15/2010
Est. Comment Period Public Notice
06/2014
Expected: 10/2014 06/2015 Kori Marchowsky
603-536-6108
kmarchowsky@fs.fed.us
Description: Relocation and redesign of all of the campsites along Tripoli Road to sites along adjacent spur roads to mitigate safety and resource concerns. Removal of hazard trees along Tripoli Road and spur roads to address safety concerns.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=31039
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. Tripoli Road, Mack Brook Road and Hix Mountain Spur Road between Exit 31 on I-93 and the town of Waterville Valley.
Waterville Valley Fan Gun Project
CE

   *NEW LISTING*
- Special use management
- Recreation management
Developing Proposal
Est. Scoping Start
04/2014
Expected: 06/2014 08/2014 Thomas Paquette
802-767-4261 x 521
tpaquette@fs.fed.us
Description: Install 8 snowmaking fan guns and 2 transformers along World Cup trail. All items would be placed on pre-cast concrete pads. A few trees would be cut at one transformer and some blasting may occur. Power and water lines would be placed in trench.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44290
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable Waterville Valley Ski Area
Waterville Valley Half-pipe Reconstruction Project
CE

   *NEW LISTING*
- Recreation management
- Special use management
Developing Proposal
Est. Scoping Start
04/2014
Expected: 06/2014 08/2014 Thomas Paquette
802-767-4261 x 521
tpaquette@fs.fed.us
Description: Remove the half pipe on Exhibition trail, restoring trail to freestyle terrain. Lower the walls, bring the trail tread back toward grade level, and use extra fill from walls to form three small landings for other terrain features.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=44289
Location: UNIT - Pemigewasset Ranger District. STATE - New Hampshire. COUNTY - Grafton. LEGAL - Not Applicable Waterville Valley Ski Area
White Mountain National Forest , Saco Ranger District R9 - Eastern Region
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Meserve Brook Watershed Restoration
CE
- Watershed management
- Wildlife, Fish, Rare plants
In Progress
Scoping Start
03/20/2014
Expected: 04/2014 06/2014 Kathleen Starke
603-447-5448
kstarke@fs.fed.us
Description: Restoration of aquatic and riparian habitat in and adjacent to Lower Meserve Brook
Location: UNIT - Saco Ranger District. STATE - New Hampshire. COUNTY - Carroll. LEGAL - Jackson Township, Carroll County, New Hampshire Lower Meserve Brook , Jackson, NH
Neuts Brook Snowmobile Trail Relocation Project
CE
- Recreation management On Hold N/A N/A Brian Johnston
603-466-2713
bmjohnston@fs.fed.us
Description: Relocate the existing snowmobile trail to the edge of the Forest Service administrative site or off the site to a private land location to eliminate safety concerns associated with the current trail location that bisects the administrative site.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=34515
Location: UNIT - Saco Ranger District. STATE - New Hampshire. COUNTY - Carroll. LEGAL - Not Applicable The trails current location runs through Bartlett Experimental Forest's administrative site, and a new location is needed to connect the trail to the Town of Bartlett..
Presidential Range Dry River Wilderness Area Trails Project
CE
- Recreation management In Progress
Scoping Start
01/17/2014
Expected: 04/2014 06/2014 Desiree Johnston
603-447-5448
dajohnston@fs.fed.us
Description: Sections of the Dry River Trail, Rocky Branch Trail and Isolation Trail in the Presi-Dry Wilderness were damaged by Hurricane Irene and need repair or a nearby relocation. Rocky Branch Shelter 2 is to be decommissioned and tent sites designated.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=41776
Location: UNIT - Saco Ranger District. STATE - New Hampshire. COUNTY - Carroll, Coos. LEGAL - Cutts Grant and Sargents Purchase in Coos County, NH, and Jackson in Carroll County, NH Sections of Dry River Trail above the footbridge, Rocky Branch Trail between Shelters 1 and 2, and intermittent sections of Isolation (west) Trail. Rocky Shelter 2 is near the jcn. of Isolation Trail.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD).

To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.

This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.